Day 4

Kuya Alfred and his co-workers started the concrete walling of the laundry area. As agreed, it will be a 5-layered concrete hollow blocks with steel fence from wall to ceiling. We used 20 pcs of square metal bar 9.45mm thickness.
the pvc pipe will serve as the exhaust for the ground and second floor level

the pvc pipe is the exhaust for the cr
square tube metal connected to the ceiling
We forgot to tell kuya alfred that we wanted to have an emergency exit in the laundry area, but he said that it's not a problem because he can just customize the metal fence. So we'll just wait for kuya alfred's update for the emergency exit door.